HOME > Division & Products > Power System Engineering > SURINAME PROJECT
- Improvement of Power Supply in the suburban area by the New Substations and Distribution Lines
- Fully Degitalized Cubicle Type New Substation
- Total Engineering Follow-up from Designing to Commissioning

Sidodadiweg S/S
33/12.6kV 10MVA

Sidodadiweg S/S
33/12.6kV 10MVA

La Pax S/S
33/12.6kV 10MVA
| Substation | Voltage | Capacity |
|---|---|---|
| La Pax S/S | 33/12.6kV | 10MVA x 1 bank Substation |
| Sidodadiweg S/S | 33/12.6kV | 10MVA x 1 bank Substation |
| B S/S | 33kV | Outgoing feeder extension |
| D S/S | 33kV | Outgoing feeder extension |
AICHI carries out the construction work under its sophisticated Quality and Safety Standard.

Civil Work

Installation of 33kV Switchgear

Withstand Voltage Test